777PACK

1000 BPH 15L Water Filling Production Line Installed in Padalarang

Project Overview

ItemDetails
LocationPadalarang
Bottle Size15L PET Bottle
Capacity1000 Bottles Per Hour
SolutionComplete Water Bottling Line
InstallationLocal Engineer Team

Project Background

This project is a 1000 BPH 15L bottled water filling production line installed in Padalarang.

The customer is a local drinking water supplier producing large-capacity bottled water for offices, restaurants, and regional distributors.

Due to the increasing demand for large-volume drinking water, the customer decided to upgrade the existing production system with a fully automated water filling line.


Production Line Configuration

PET Bottle Blowing Machine

The bottle blowing machine converts PET preforms into 15L PET bottles through heating and high-pressure compressed air.


3-in-1 Rinsing Filling Capping Machine

This machine integrates bottle rinsing, filling and capping into one unit to ensure hygienic water production.


OPP Labeling Machine

The OPP labeling machine applies roll film labels using hot melt glue technology.


Production Process

1 PET preforms are blown into bottles
2 Bottles are rinsed and filled with purified water
3 Bottles are sealed with caps
4 Bottles are labeled automatically


Installation and Commissioning

Our local engineer team in Indonesia completed the installation and commissioning of the production line.

After installation the system achieved stable operation and improved production efficiency.

Leave a Reply

Your email address will not be published. Required fields are marked *

Contact With Us

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.